Energy Site Team Communication: A Guide for Line, Substation, Wind and Solar Crews

Team communication on an energy site tolerates fewer mistakes than coordination on a construction site. On a power line, in a substation, or at a wind or solar plant, a single misunderstood message can mean a line being energised at the wrong moment. These sites are also usually far from towns: crews spread out over kilometres and the coverage map stays blank. In this article we cover, step by step, what makes energy sites different from a communication point of view, which information must reach whom and how when a line is de-energised and re-energised, the rules on lone working, the communication side of the emergency plan, and how to choose channels for sites without coverage.

In short

  • The most critical message on an energy site is the moment power is cut and the moment it is restored; that message must be written, confirmed and recorded.
  • The maintenance procedures of Türkiye’s Ministry of Energy and Natural Resources for 0–36 kV distribution installations require that no lone working takes place during maintenance under any circumstances.
  • A short briefing before work starts makes sure everyone understands the hazards, work steps, energy control and protective equipment in the same way.
  • Türkiye’s Regulation on Emergencies at Workplaces makes the communication method a written part of the emergency plan.
  • Choose the channel for the farthest point of the site; radio carries voice coordination, a mesh network carries written messages, location and records.

What makes an energy site different?

Three risks are present at once on an energy site: voltage, height and distance. A 2025 study on occupational health and safety at wind energy sites by Köse, Uzun and İnci of İzmir Bakırçay University notes that physical risks such as falling from height, electric shock, lightning strikes, fire and icing stand out during installation and maintenance. Drawing on data from the Caithness Windfarm Information Forum (CWIF), the same study reports that 3,287 occupational accidents were recorded at wind energy sites in different parts of the world between 2000 and 31 March 2023.

Distance is a separate problem. The UK Health and Safety Executive (HSE), in its guidance on managing the risks of working alone, lists a workplace in a rural or isolated area among the factors to be assessed. Power lines, wind turbines and solar plants are exactly in such places. Once a crew is in the field, mobile phones often have weak coverage or none at all, while voice radio is limited by range and terrain.

Communication needs by site type

The table below summarises the four most common site types and the message that matters most on each:

Crew distribution and communication needs by energy site type
SiteHow the crew spreads outWhat makes communication hardKey message
Transmission and distribution lineAlong the line, pole to poleLong corridors, valleys and forest, distance from townsSwitching instructions, who is on which pole
SubstationIn one facility, across different baysMetal structures and concrete buildingsSwitching sequence, lockout and tagging information
Wind power plantTurbine to turbine, inside the tower and on top of the nacelleHeight, ridge and hilltop terrain, weatherStatus of the crew working aloft, weather warnings
Solar power plantAcross a large panel field, at inverter and transformer pointsSize of the area, rural locationFault location, zone-based task allocation

On the wind side the scale is growing too: according to the same study, rotor diameters were around 20 metres in the 1980s and today reach 150–200 metres. The link between a crew inside a turbine or on the nacelle and the crew on the ground must not be the weakest point of the site.

De-energising and re-energising: the most critical message

The Maintenance Procedures for High-Voltage Electrical Installations (0–36 kV) published by Türkiye’s Ministry of Energy and Natural Resources (ETKB) set out a clear sequence for maintenance on distribution installations. Under Article 5 of the document, before work starts the power is cut, the absence of voltage is checked with suitable devices, all switchgear is opened, every live part that could be energised is short-circuited and earthed, warning signs are posted, locking devices are applied and “the relevant places are informed”. When the work ends, the earthed parts are returned to their previous state and the steps taken are checked before power is restored. The same article also requires a record of who carried out the maintenance, when, and under which work order.

Every step in this sequence is a communication step. As an international example, the US Occupational Safety and Health Administration’s 29 CFR 1910.269 standard on electric power generation, transmission and distribution ties the release of a clearance on a de-energised line to four steps: notify each employee under the clearance of the pending release, ensure that all of them are clear of the lines and equipment, ensure that the protective grounds have been removed, and only then report this to the system operator and release the clearance.

In the field, this translates into a flow like the following:

  1. One person in chargeFor each job, a single crew lead requests and releases the de-energisation; their name is announced to the whole crew in writing.
  2. Confirmation of the cutThe control centre or the operations manager confirms in writing that power is off; after checking for the absence of voltage, the crew lead sends a “starting work” message.
  3. Work with locationWho is working on which pole, turbine or bay is visible on the map; the information is updated when the crew moves.
  4. Completion reportsEach sub-crew separately reports that it has finished, moved clear of the line and removed its earthing.
  5. Re-energisingOnce all reports are in, the crew lead tells the control centre the line is clear; power is restored only after this message.
  6. RecordEvery message is stored with a timestamp and linked to the work order record.

We explained in detail why timestamped records matter in an after-action review in our article on operation data logging.

The pre-job briefing

The ETKB maintenance procedures require that assigned staff are informed about the scope of the work before maintenance and that safety instructions are kept in a visible place at the installation. OSHA 1910.269 also defines the content of that briefing: the employee in charge conducts a briefing with the crew before each job starts, covering at least the hazards of the job, work procedures, special precautions, energy-source controls and personal protective equipment requirements. Additional briefings are required if significant changes that might affect employee safety occur. A formal briefing is not required for an employee working alone, but the tasks must be planned as if one were required.

If crews go out in separate vehicles at different times, a written summary of the briefing should be sent to everyone at the same moment. You can find the structure we suggest for the chain of responsibility and shift handover in our article on construction site team communication; the same logic can be adapted to energy sites.

Lone working and remote sites

The wording of the ETKB maintenance procedures is unambiguous: “No lone working shall take place under any circumstances while maintenance work is carried out.” OSHA 1910.269 likewise requires at least two employees to be present for work such as installing, removing or repairing lines energised at more than 600 volts. HSE guidance states that certain high-risk work requires at least one other person, and includes work near exposed live electricity conductors.

Even a two-person crew can be alone in the field: one at the top of a turbine, the other below; or both together, kilometres from the control centre. HSE’s page on training, supervision and monitoring says lone workers must be monitored and kept in touch with, and lists methods such as knowing where lone workers are with pre-agreed intervals of regular contact, devices for raising the alarm operated manually or automatically, and a reliable system to ensure a lone worker has returned to base once the task is complete. Help arrives late on a remote site; this is why OSHA requires at least two first-aid trained persons for field work involving two or more employees on energised lines, and at a remote substation requires every employee at the work location to be trained.

The common outcome of these rules is that the crew lead must be able to see at all times who is where and when they last reported their status. An emergency alert sent with a single action carries the worker’s name and location to the crew and removes the time spent searching.

The communication side of the emergency plan

Under Article 10 of Türkiye’s Regulation on Emergencies at Workplaces, the employer determines and puts in writing emergency response methods such as warning, search, rescue, evacuation, communication, first aid and firefighting. The same article requires nearby workplaces and adverse effects from the surroundings to be taken into account when these methods are set. Article 5 lists among the employer’s duties making arrangements for liaison with organisations outside the workplace, especially for first aid, emergency medical response, rescue and firefighting.

Three articles matter particularly for energy sites. Article 11 requires the shift pattern to be taken into account when assigning support staff to emergency teams, and a list with their names, titles, areas of responsibility and contact details to be posted at the workplace. Article 13 provides that, outside mining workplaces, drills are held at least once a year. Article 17 requires that, where several employers share the same work area, the emergency plan is prepared jointly by the employers. A plant operator, a maintenance contractor and a line crew working on the same site is a typical example. A joint plan stays on paper without a shared communication channel and an alert flow that everyone knows.

Choosing channels for an energy site

Choose the channel not for the average point of the site, but for the farthest pole, the tallest turbine and the valley where coverage ends:

Comparison of communication channels for energy sites
ChannelStrengthLimit on an energy site
Mobile phone and messaging appEveryone has one, fast where there is coveragePatchy coverage on rural lines and hilltop sites; no organisational record keeping
RadioInstant voice coordinationTerrain and range; leaves no written trace
Satellite phoneReaches the outside world from places with no infrastructureExpensive for in-team coordination and requires calling people one by one
Mesh networkDevices relay each other; written messages, location, status and recordsDoes not carry voice; distant points need a relay station plan

For most energy crews the right answer is not a single channel but two that complement each other: radio carries instant voice coordination, while the mesh network carries switching confirmations, location, status reports and the record. We have gathered use across energy, industrial and construction sites on our operational communication page.

Our approach

When we designed BosNets, we treated a site without coverage as the default, not the exception. Every BosMag that joins the network is also a relay: as the crew spreads out along the line or between turbines, the devices in between carry the message, and a packet can make up to five hops within the network. The single-hop range between two devices is 5 km in open terrain; in normal field use the device battery lasts 48 hours.

For distant points we developed the solar-powered BosBase relay station, which needs no installation; it reaches 20 km in open terrain and can be placed on a ridge or on a vehicle roof. The devices operate in the 869.4–869.65 MHz licence-free band, so the organisation does not need a separate frequency allocation. Where there is mobile coverage the system also uses the internet; where there is none it carries on over the mesh.

We do not aim to take the place of radio; voice coordination is radio’s job. We carry written instructions, location and emergency alerts, and log every message with a timestamp. The BosApp map opens on sites with no coverage, and the browser-based BosLog management interface brings task assignment and the record of switching messages together at the control centre.

— Emir Tanrıver, BosNets co-founder

Frequently asked questions

Can switching instructions be given verbally?

Verbal instructions are unavoidable in the field, but they are not enough on their own. The information that power is off, that work is finished and that the crew is clear of the line should be closed with a written confirmation and stored with a timestamp. The ministry’s maintenance procedures also require a record of who carried out the maintenance, when and under which work order.

Can someone work alone on a power line?

Under the maintenance procedures of Türkiye’s Ministry of Energy and Natural Resources for 0–36 kV distribution installations, no lone working takes place during maintenance under any circumstances. Set the rules specific to your installation and work together with your occupational safety specialist.

How does a crew communicate on a wind or solar site with no coverage?

With a mesh network that does not depend on central infrastructure and in which devices relay each other. As the crew spreads out, the devices carry the message in a chain; a relay station placed on a ridge or in the middle of the site extends coverage. You can keep using radio for voice coordination.

How often should emergency drills be held on an energy site?

Under Türkiye’s Regulation on Emergencies at Workplaces, drills are held at least once a year at workplaces other than mines. Running the drill from the farthest point of the site and with a no-network scenario shows whether your communication method actually works.